Safeco Surety v. J.P. Southwest Concrete, Inc. (Tex.App.- Houston [1st Dist.] Apr. 2,
2009)(Alcala)(consequences of failure to disclose evidence, failure to plead properly, trial by consent,
release as affirmative defense, lost profit damages)
AFFIRM TC JUDGMENT IN PART, REVERSE TC JUDGMENT IN PART, AND REMAND CASE TO TC FOR
FURTHER PROCEEDINGS: Opinion by Justice Alcala
Before Chief Justice Radack, Justices Alcala and Hanks
01-07-00904-CV Safeco Surety and C.A. Walker, Inc. v. J.P. Southwest Concrete, Inc.
Appeal from 189th District Court of Harris County
MEMORANDUM OPINION
Appellants, C.A. Walker Construction Company and Safeco Surety (collectively "Walker"), appeal from
the trial court's judgment awarding appellee, J.P. Southwest Concrete, Inc. ("J.P."), $47,000 in actual
damages, as well as attorney's fees and pre- and post-judgment interest. In its first three issues,
Walker contends the trial court erred in the amount of damages awarded to J.P. because (1) the
damages award is not supported by the evidence, (2) the language of the contract between Walker
and J.P. precludes at least some of the consequential damages sought by Walker, and (3) J.P. did not
plead for the damages the trial court awarded. In its fourth issue, Walker contends the trial court
improperly rendered judgment against Walker on its counterclaim.
We conclude that Walker waived its challenge to the counterclaim due to inadequate briefing, and the
trial court erred in its determination of the amount of the damages award. We therefore affirm in part
and reverse and remand in part.
Background Walker was the general contractor on a construction project for the Spring Branch
Independent School District. J.P. was a subcontractor on the project and contracted to perform
concrete work, including drilling pier holes and pouring concrete piers. Among other requirements, the
contract provided that extra work performed by J.P. outside the scope of the contract must have
Walker's approval and signature in a written change order. The contract provided for Walker to pay
$243,000 in exchange for J.P.'s performance of "all concrete work" for the project, including "concrete
slabs, walks and paving" and "providing and placing all concrete related: concrete, rebar, vapor
barrier, form boards, expansion materials, and tie-wires." The contract did not mention site work or
removal of existing obstructions. According to Jeff Pantle, J.P.'s president, J.P. was not responsible for
site clearing, demolition, and subsoil debris removal, and those jobs should have been done by the
time J.P. was to do the concrete work.
In September 2004, when J.P. began its work for Walker, it encountered severe subsoil obstructions
while attempting to drill pier holes. Pantle and Donnelly, J.P.'s superintendent, both described
numerous obstructions J.P. encountered while attempting to drill pier holes. Walker instructed J.P. to
prepare and submit written change orders to cover the removal of the obstructions. J.P. did submit a
number of written change orders for work outside the scope of the contract. However, Walker only
approved some of these orders.
As work progressed, J.P. submitted applications for payment along with supporting documentation. As
of December 2004, J.P. had been paid $57,349.25. J.P. submitted another application for payment
seeking $79,796 for January. Later, J.P. sought a payment of $17,099 for work done in February.
Walker did not pay J.P. until March 16, 2005, when it paid $84,756.35. In exchange for the March 16,
2005 payment, Pantle, on behalf of J.P., executed a "Subcontractor Affidavit of Payment and Partial
Release of Lien."
After the March 16, 2005 payment, the amount remaining to be performed under the contract was
$132,043.40 and J.P. continued to work for Walker. Walker told J.P. that subsoil debris and
obstructions had been removed and requested it continue drilling pier holes. J.P. went to the site,
bringing with it another subcontractor that had drilling equipment, but was unable to perform work due
to subsoil debris and obstructions. Walker acknowledged that it owed J.P. money as payment for this
work that was done March 22, 2005, but only for the amount of $2,848.
For several months, J.P. attempted to get paid for the work it had done. J.P. sent a demand letter
stating Walker owed J.P. $77,501, which was for $19,501 for completed, unpaid work and $58,000 in
lost profits. When Walker did not pay the amount requested, J.P. filed suit for that same amount.
Walker requested a disclosure under rule 194.2(d) of "the amount and any method of calculating
economic damages." (1) J.P. replied,
Damages: $19,501.00 for billed unpaid work,
$58,000.00 lost profit,
Total: $77,501.00
At the bench trial, Pantle testified J.P. was seeking $19,501 for unpaid work and $58,000 for lost
profits.
Several weeks after the trial concluded, J.P. filed a motion for entry of judgment. Within this motion, J.P.
asserted total damages in the amount of $74,059.52 for the following:
$17,099.00 for unpaid contract work in February 2005[;]
$21,748.52 for unpaid contract work in March 2005[;]
$8,389.00 for funds retained by Walker from previous payments[; and]
$26,823.00 for extra work completed for unsigned change orders.
J.P. requested that the $74,059.52 be reduced to $69,099.17 to allow for a credit for the amount by
which the March 16, 2005 payment exceeded the requested payment for the January work. J.P. then
requested that the $69,099.17 be increased to $72,699.17 to compensate for $3,600 for Transit Mix's
attorney's fees paid by J.P. In addition, instead of the $58,000 originally sought for lost profits, J.P.
reduced its lost profits claim to $26,499.05. The proposed judgment submitted by J.P. stated the actual
damages as the sum of the unpaid work and Transit Mix attorney's fees only; it did not include the
reduced lost profits. The trial court rendered judgment in favor of J.P., awarding $47,000 in actual
damages. The trial court did not explain how it reached the $47,000 figure, nor did it make findings of
fact and conclusions of law. The Amount of Damages
Walker challenges the $47,000 amount for damages by claiming any damages incurred prior to March
16, 2005 are disclaimed by J.P. in a release; the evidence does not support the lost profits claim; J.P.
cannot recover damages from Walker for Transit Mix's lawsuit against J.P.; and J.P. cannot recover
damages never disclosed to Walker until after trial. We agree with Walker that it would have been
improper for the trial court to render its damages award by taking any of these damages into account in
its award to J.P.
A. Release
As part of its first issue, Walker contends, "The damage award is not supported by the evidence
introduced at trial" because J.P. agreed to release all damages stemming from any payments due
prior to the date the release was executed, on March 16, 2005, which left only $2,848 in damages for
work done March 22, 2005.
1. Sufficiency of Pleadings and Trial by Consent
J.P. contends Walker waived any issue concerning the release because release is an affirmative
defense that was not pleaded by Walker.
The Texas Rules of Civil Procedure require certain defenses, including the defense of "release," to be
affirmatively pleaded. Tex. R. Civ. P. 94. Generally, an affirmative defense is waived if it is not pleaded.
Alvarado v. Wingfoot Enters., 53 S.W.3d 720, 725 (Tex. App.--Houston [1st Dist.] 2001) (quoting
Shoemake v. Fogel, Ltd., 826 S.W.2d 933, 937 (Tex. 1992)) rev'd on other grounds by 111 S.W.3d
134 (Tex. 2003). However, "[u]npleaded claims or defenses that are tried by express or implied
consent of the parties are treated as if they had been raised by the pleadings." Hartford Fire Ins. Co. v.
C. Springs 300, Ltd., No. 01-06-00065-CV, 2008 WL 2208887, at *6 (Tex. App.--Houston [1st Dist.]
May 29, 2008, no pet. h.) (citing Roark v. Stallworth Oil & Gas, Inc., 813 S.W.2d 492, 495 (Tex. 1991)).
"The party who allows an issue to be tried by consent and who fails to raise the lack of a pleading
before submission of the case cannot later raise the pleading deficiency for the first time on appeal."
Id. (citing Roark, 813 S.W.2d at 495). "Moreover, '[w]hen issues not raised by the pleadings are tried
by express or implied consent of the parties, they shall be treated in all respects as if they had been
raised in the pleadings.'" Id. (quoting Tex. R. Civ. P. 67). "To determine whether an issue was tried by
consent, we examine the record not for evidence of the issue, but rather for evidence of trial of the
issue." Id. (citing Case Corp. v. Hi-Class Bus. Sys. of Am., Inc., 184 S.W.3d 760, 771 (Tex.
App.--Dallas 2005, pet. denied)). "A party's unpleaded issue may be deemed tried by consent when
evidence on the issue is developed under circumstances indicating that both parties understood the
issue was in the case, and the other party failed to make an appropriate complaint." Id. (citing Case
Corp., 184 S.W.3d at 771).
Here, it is undisputed Walker did not plead release as an affirmative defense. We therefore must
examine the evidence of this issue being tried by consent. Id. In opening statements, Walker's counsel
raised the issue of the release. The release was admitted into evidence without objection. Walker
testified the March payment was made despite J.P. not providing all the required documentation and
included amounts for work that had not been done by J.P. In response to questions from the judge,
Walker's counsel asserted the plain language of the release indicated J.P. acknowledged that, as of
March 16, 2005, it had been paid for all work. Pantle was cross-examined concerning the release,
acknowledging he signed it. J.P.'s counsel then conducted a re-direct examination of Pantle
concerning the circumstances surrounding the signing of the release. The trial court did not hear
closing arguments, but instead discussed a number of issues with counsel. The release came up
several times and both sides presented their theories and arguments concerning the proper
interpretation and effect of the release. J.P. did not complain of the lack of pleadings to support the
affirmative defense of release before the trial court, raising the issue for the first time in its brief to this
Court.
We conclude the issue of release was tried by consent because the record shows the release was
introduced at the trial without objection, witnesses were examined concerning the release, both parties
discussed and argued the meaning and effect of the release to the trial court, and J.P. did not make
any complaint concerning the lack of pleadings to support the defense of release. See Hartford Fire
Ins. Co., 2008 WL 2208887 at *7 (concluding issue tried by consent when issue "was raised several
times during the trial" and no objection to lack of pleadings made until charge conference).
2. Consequence of the Release
Walker contends J.P. released all damages stemming from any payments due prior to March 16,
2005, the date the release was executed.
A release is a type of contract and is construed according to the rules governing contracts generally.
Baty v. ProTech Ins. Agency, 63 S.W.3d 841, 848 (Tex. App.--Houston [14th Dist.] 2001, pet. denied).
Our primary concern when construing a written contract is to ascertain the true intent of the parties, as
expressed in the contract itself. Coker v. Coker, 650 S.W.2d 391, 393 (Tex. 1983). In determining
intent, we must look to the contract, not what the parties allegedly meant. Union Pacific R.R. v. Novus
Int'l, Inc., 113 S.W.3d 418, 421 (Tex. App.--Houston [1st Dist.] 2003, pet. denied). An unambiguous
contract will be enforced as written. David J. Sacks, P.C. v. Haden, 266 S.W.3d 447, 450 (Tex. 2008)..
Parol evidence may not be introduced to create an ambiguity or to alter the intent of the parties as
expressed in the instrument. Id.
The release signed by Pantle on behalf of J.P. acknowledges payment of $84,756.35 "and other good
and valuable consideration." It then states,
Subcontractor waives, releases, relinquishes and discharges all known and unknown causes of action,
including, but not limited to those arising out of contract, by statute, in tort or otherwise, and waives,
releases, relinquishes and agrees to discharge any suits, debts, accounts, bonds, contracts, promises,
damages, liens, encumbrances, judgments, claims and demands whatsoever, in law or equity, which
are against the Contractor . . . that the Subcontractor now has or might hereinafter obtain that relates
directly or indirectly to the aforesaid relationship, Contract, and/or Project.
. .
Subcontractor and I hereby acknowledge that Subcontractor has previously been paid from Contractor
$57,349.25 for the above named job, and this payment constitutes full payment for the work performed
to date and any and all change orders or claims for additional work performed. . . .
J.P. challenges the release by pointing to Pantle's testimony and letters written by Walker that state that
the March 16, 2005 payment is only for work done in January 2005. The release itself, however, plainly
states that the $84,756.35 "payment constitutes full payment for the work performed to date and any
and all change orders or claims for additional work performed." The testimony and letters are parol
evidence that cannot properly be considered to change the written terms of the release. See David J.
Sacks, P.C., 266 S.W.3d at 451.
J.P. also asserts "the numbers at the top of right 0105, is the date January 2005." The portion of the
release that J.P. points to states, "Date: 03/16/2005 Payment Request: 0105R." The date of the
release clearly is March 16, 2005, which is also the date Pantle signed the release. We conclude that
by signing the release, J.P. acknowledged it was fully paid for all work it had performed as of March 16,
2005.
We sustain Walker's first issue to the extent that the trial court would have erred by including any
amounts for work done before March 16, 2005 because J.P. released its claim for those amounts.
B. Lost Profits Damages
Within its first issue, Walker contends J.P.'s claim for lost profits is not supported by the evidence.
Specifically, Walker contends lost profits must be proved with reasonable certainty and J.P. failed to do
so, because J.P.'s claim for lost profits assumed a 25 percent profit margin based on speculation.
1. Recovery of Lost Profits
In a breach-of-contract case, damages are usually measured by the "benefit-of-the-bargain" standard,
intended to put the party seeking damages in as good a position as if the contract had been
performed. Bowen v. Robinson, 227 S.W.3d 86, 96 (Tex. App.--Houston [1st Dist.] 2006, pet. denied).
Benefit-of-the-bargain damages may include reasonably certain lost profits. Id. "Lost profits are
damages for the loss of net income to a business and, broadly speaking, reflect income from lost
business activity, less expenses that would have been attributable to that activity." Id. (citing Miga v.
Jensen, 96 S.W.3d 207, 213 (Tex. 2002)). In other words, "[l]ost profits must be based on net profits,
not gross revenues." Texaco, Inc. v. Phan, 137 S.W.3d 763, 771 (Tex. App.--Houston [1st Dist.] 2004,
no pet.).
To recover lost profits, the party seeking them must prove them with reasonable certainty and
competent evidence. Bowen, 227 S.W.3d at 96. "Generally, lost profits are properly calculated by
deducting the costs of the injured party's performance supported by data from the actual contract
price." Id. (citing Cmty. Dev. Serv., Inc. v. Replacement Parts Mfg., Inc., 679 S.W.2d 721, 725 (Tex.
App.--Houston [1st Dist.] 1984, no writ)). "However, a witness may also prove lost profits by testifying
as to what his profit would have been, based on his knowledge of the cost of performance of each
element of the contract and subtracting the total of such costs from the contract price." Id. (quoting
Cmty. Dev. Serv., Inc., 679 S.W.2d at 725). "What constitutes reasonably certain evidence of lost
profits is a fact intensive determination. At a minimum, opinions or estimates of lost profits must be
based on objective facts, figures, or data from which the amount of lost profits can be ascertained." Id.
at 97 (quoting Holt Atherton Indus., Inc. v. Heine, 835 S.W.2d 80, 84 (Tex. 1992)).
2. Evidence of Lost Profits
At trial, Pantle testified J.P. was seeking $58,000 in lost profits. The following testimony is the only
calculation Pantle provided:
Q: Okay. How did you arrive at the $58,000 lost profits?
A: I based it on the contract amount, the approved change orders that Walker did approve. Then I
added in the unchanged--the unsigned change orders. I came up with a total, subtracted it from what
had already been paid, came up with a balance and then put a 25 percent net markup on that.
Q: How--what do you mean by 25 percent?
A: On a job, on this particular job, I had a 25 percent--not gross--but net markup.
Q: And the $58,000 lost profits reflects that 25 percent flat figure?
A: Well, it--it's that and the change orders and such.
J.P. contends this evidence is "based on objective facts from which the amount of the lost profits can
be ascertained," citing Texaco, Inc. v. Phan as support. In Texaco, this Court found the affidavit
testimony of the owners of a gas station and convenience store was no evidence to support an award
of lost profits. Texaco, Inc, 137 S.W.3d at 772. The owners stated they had a profit margin of 30
percent, basing this assertion on the prior 17 months of operation at their stores. Id. However, this
Court noted that the owners did not define "profit margin" or address expenses. Id. The bare assertion
of a profit margin of a certain percent, even one based on prior experience, was not sufficient evidence
to support an award of lost profits. Id. at 772-73.
Here, like the owners in Texaco, Pantle did not address J.P.'s expenses. See id. at 772. Pantle did not
testify what expenses J.P. would incur in performing the contract. Rather, he simply stated, "On a job,
on this particular job, I had a 25 percent--not gross--but net markup." Pantle did not "testify[] as to what
his profit would have been, based on his knowledge of the cost of performance of each element of the
contract and subtracting the total of such costs from the contract price." Bowen, 227 S.W.3d at 96. J.P.
failed to present "objective facts, figures, or data from which the amount of lost profits can be
ascertained." See id. at 97. We conclude the evidence is factually insufficient to support an award of
lost profits. See id.; Texaco, Inc, 137 S.W.3d at 772-73.
We sustain Walker's first issue to the extent that the trial court would have erred by including any
amounts for lost profits because the evidence did not show objective facts, figures, or data from which
the amount of lost profits could be ascertained. Further, any lost profits incurred before March 16, 2005
are not properly included in the award.
C. Consequential Damages
In its second issue, Walker asserts the contract language precluded J.P.'s recovery of its claimed
damages incurred by paying the claims asserted against J.P. by Transit Mix. Walker contends that part
of the $58,000 lost profit award sought by [J.P] was a claim for consequential damages for costs
associated with settling a lawsuit asserted against it by one of its subcontractors, Transit Mix[,]" a
company that sued J.P. to recover payment for supplies.
The contract provides,
In the event suit is filed by any person, firm or corporation asserting a claim or lien for labor, services or
materials used or purchased for use in the work covered by this contract, [J.P.] will, at its own cost and
expense, including counsel fees, defend such suit and pay any judgment rendered therein.
The plain language of the contract excuses Walker from paying any damages for a suit filed against
J.P. by Transit Mix for services or materials, or the attorney's fees incurred by Transit Mix and paid by
J.P. See David J. Sacks, P.C., 266 S.W.3d at 450 (stating unambiguous contract will be enforced as
written). Additionally, to the extent the damages award included materials provided before March 16,
2005, the release executed by J.P. precludes such an award. We sustain Walker's second issue to the
extend the trial court may have included damages for Transit Mix's attorney's fees.
D. Unpleaded and Undisclosed Elements of Damages
In its third issue, Walker contends the trial court erred to the extent it based the award of damages to
J.P. on damages not pleaded or disclosed prior to trial. J.P. does not reply to Walker's issue
concerning the failure to disclose the amount and method of calculating damages, instead asserting,
"The damages models presented by [J.P.] [w]as supported in the testimony of Pantle and succinctly set
out at CR000089, in [J.P.'s] Motion for Entry of Judgment."
Texas Rule of Civil Procedure rule 194.2(d) provides that a party may request disclosure of "the
amount and any method of calculating economic damages." Tex. R. Civ. P. 194.2(d). Comment 2 to
the rule provides that subsection (d) is "intended to require disclosure of a party's basic assertions,
whether in prosecution of claims or in defense." Id. cmt. 2. As an example of the required disclosure,
comment 2 notes, that, in a claim for damages suffered in a car accident, the plaintiff would be required
to state how loss of past earnings and future earning capacity was calculated. Id.
Rule 193.6(a) provides, "A party who fails to make, amend, or supplement a discovery response in a
timely manner may not introduce in evidence the material or information that was not timely disclosed."
Tex. R. Civ. P. 193.6. The purpose behind this rule is to prevent trial by ambush. Harris County v. Inter
Nos, Ltd., 199 S.W.3d 363, 367 (Tex. App.--Houston [1st Dist.] 2006, no pet.) (citing Aetna Cas. & Sur.
Co. v. Specia, 849 S.W.2d 805, 807 (Tex. 1993)). "Absent a showing of good cause, lack of unfair
surprise, or lack of unfair prejudice, rule 193.6 mandates exclusion of the undisclosed material or
information." Id. "The burden of establishing good cause or the lack of unfair surprise or unfair
prejudice is on the party seeking to introduce the evidence . . . ." Tex. R. Civ. P. 193.6(b); Harris
County, 199 S.W.3d at 367.
In the demand letter, petition, response to the request for disclosure under rule 194.2(d), and at trial,
J.P. sought damages for $77,501, an amount consisting of $19,501 for unpaid work and $58,000 for
lost profits. However, the request for $19,501 for unpaid work was changed after the trial to become a
request for damages for $17,099.00 for unpaid contract work in February 2005; $21,748.52 for unpaid
contract work in March 2005; $8,389.00 for funds retained by Walker from previous payments; and
$26,823.00 for extra work completed for unsigned change orders. The request for $58,000 for lost
profits was reduced after the trial to $26,499.05. Additionally, after the trial, a new request for damages
was made by J.P. for $3,600 for Transit Mix's attorney's fees paid by J.P. We conclude the post trial
requests for damages and attorneys fees violated rule 193.6 because J.P. failed to amend its
responses to requests for disclosure, and rule 194.2(d) because J.P. failed to disclose the amount and
method of calculating economic damages. Tex. R. Civ. P. 193.6, 194.2(d); see also Harris County, 199
S.W.3d at 368 (holding trial court did not abuse discretion in excluding evidence concerning Harris
County's calculation of fair market value in condemnation case because Harris County did not present
evidence of good cause, lack of unfair surprise, or lack of unfair prejudice in failing to correct erroneous
response to request for disclosure). We sustain the third issue to the extent the trial court erred if it
based the damages award on the undisclosed method of calculating economic damages. See id.
E. Conclusion
Although the trial court did not make findings of fact and conclusions of law to show how it reached the
$47,000 damages figure, we conclude that the amount of the award is erroneous because the figure
could not have been reached without taking into consideration amounts that were disclaimed by the
release, were for lost profits, were for Transit Mix's lawsuit, or were not properly disclosed before post
trial. We must therefore remand the cause for a new damages determination.
Walker's Counterclaim
In its fourth issue, Walker contends, "Although the trial court never expressly disposed of [Walker's]
counterclaim for breach of contract, the court implicitly ruled in favor of [J.P.]." Walker, however, does
not cite to a single authority in its discussion of this issue. We hold error, if any, is waived due to
inadequate briefing. See Tex. R. App. P. 38.1(i) ("The brief must contain a clear and concise argument
for the contentions made, with appropriate citations to authorities and to the record."); Tesoro
Petroleum Corp. v. Nabors Drilling USA, Inc., 106 S.W.3d 118, 128 (Tex. App.--Houston [1st Dist.]
2002, pet. denied) (holding rule 38 not satisfied by "merely uttering brief conclusory statements,
unsupported by legal citations").
We overrule Walker's fourth issue.
Conclusion
We affirm that portion of the trial court's judgment rendering a take-nothing judgment on C.A. Walker
Construction and Safeco Surety's counterclaim. We reverse that portion of the trial court's judgment
awarding damages to J.P. Southwest Concrete, Inc. and remand this cause to the trial court for the
limited purpose of conducting a new trial on the issue of damages.
Elsa Alcala
Justice
Panel consists of Chief Justice Radack and Justices Alcala and Hanks.
1. Tex. R. Civ. P. 194.2(d).